For some old PIR -Av qty in MD04 is not getting calculated

32 Views

Hi Friends,

I have came across a strange observation.

I have a new material for which strategy is one Z strategy (copy of 40-some minor change) , for this material I have created PIRs on several dates. In stk/ reqmt list I can see all PIRs.

But for few initial PIRs (till 12 th august 11) , available quantity calculation (column in stk/ Reqmt list) is not happening.

For PIRs 0n & after 13th august , Av qty calculation is happening.

I could not understand the system behaviour. Can you please let me know why these old PIRs (older than approx 45 days) , are not taking part in calculation.

Thanks & Regards,

Sandeep