Hi experts,

We are having inconsistency values between reports S_ALR_87100185 ​​and CJIE.

I read the message posted in , but not solved our problem.

In fact, all reports made ​​to show different values ​​when analyzed in CJI3 (eg S_ALR_87100188).

This may be related with the database currency (currency translation) that is used in the report ?

Regards,

Alessandra

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

I ran the CJEN but the project is ok. In fact all projects are showing differences in S_ALR_87100185 vs CJIE.I think the problem is in reports S_ALR_...... because de CJIE displays the correct values.

I´m thinking of create a new report (using S_ALR_87100185 as a model) and change de database currency to BRL. It´s possible to do this ? The user ask me to include the period in the report filter too.

Regards.

Former Member
0 Kudos

Hi,

You can develop reports similar to S_ALR_87100185, if that's what is needed. You will have two options. One to write a ABAP report that full fils your reuirements and the second would be to develop a report painter report (using CJE1 / CJE4). In the report painter you have the option of selecting the currency like controlling area, object currency etc.

On a separate note I would also suggest to check the exchange rate settings once, since you mentioned that all projects are showing difference in S_ALR_87100185 report.

Regards

Sreekanth

former_member230675
Active Contributor
0 Kudos

first run CJEN and see any value category miss match is there or not. While running system will show you the warning message if any Cost element is missing from value category.

Please also run some cost element report and verify, if you do not want to include value from some of the cost elements in the report create a suppress value category and suppress them.

You can also filter CJI3 report by excluding all the business transactions those are related to settlements (settlement to AUC / settlement to superior WBSE / settlement reversal etc..etc..)

Former Member
0 Kudos

Hi,

There are many other posts as well in this regard and if you search once more you should able to find them. Some of the possibilities that you can check are the value category set up and see if any cost elements are missed out, run CJEN to clear any inconsistancies, check the report profiles / layout / filters etc.

Regards