Sep 25, 2011 at 09:06 PM

Scheduling time

18 Views

dears

When i created a production order with following prerequisites

Work center with 100% utilization with 8 hrs in operation

Only one operation

set up time is 1 HR,Processing time is 1 hr,tear down time is 1 hr

there is no queue time,move time in routing

control key is pp01

forward scheduling

now in scheduling for set up time system is making additional 7.5 min for all operation(set up.machine and tear down)

From were and why the system is adding 7.5 min additional time in operation

Regards

FAI