Hi All
We have a requirement to control Purchase Order amount , so that it should not exceed the allocated Budget , currently the Error message is coming when we are doing FG delivery /PGI & we are converting PR generated from PS into PO
Please tell the complete steps (customization & Master Data Control Factors) for mapping the availability check of Budget when we are creating purchase order & not during PGI.
Thanks
Cybrat24
Go to Define Tolerance Limits customizing transaction to setup budget control on PO. Refer to SAP Help for assistance on how to perform the configuration.