I have incorrectly set up the base unit of measure and I need to change that one.When I change the base UOM in MM02 it is giving me an error "UOM can't be changed choose display errors". It shows that Material used in Routing.

But Routing already deleted. The routing has been set as deletion indicator in table MAPL.

Please help to resolve the issue.

Regards,

Senthil

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Sep 23, 2011 at 02:50 PM

    You must archive the record off.

    FF

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 23, 2011 at 10:10 PM

    Hi,

    Go to Routing --> Edit and Select "Delete" and save the Routing. This will delete Routing at header level and solve your problem.

    Regards,

    Gaurav Mehra

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.