Delivery Item

The Delivery is generated from STO/Sales Order. I have 3 Item in the Delivery.

Can I do the Post Good Issue per Item?

I.e. I only do the Post Good Issue for item 2 because no stock avaiable for item 1 and 3.

If yes, where can I find the Post Good Issue date for item 2?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 23, 2011 at 02:28 AM

    Hi,

    Partial PGI is not possible and it applies to whole document.To do post goods issue, Delivery quantiy and Picking quantity must be same.So, if you want partial to post then,open the Delivery doc and reduce the Delivery quantity.

    Regards,

    Madhu.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      PArtial Pgi is possible, just change the delivery quantities and pick the same qty you want to pgi. Untless all the materials quantities are fully referenced from the SO into the Delivery and picked the pgi will be partial complete.

      Regards,

      Anand

      Edited by: Anand Mathur on Sep 27, 2011 7:27 AM

  • avatar image
    Former Member
    Sep 23, 2011 at 05:39 AM

    Hi Mymmph -

    you can delete line item1 and item 3 . and do post goods issue.

    Once material is available .you can create a new delivery with reference to that sales order. So that it will bring items which are not delivered

    Hope It helps

    Arunkumar.S

    Add comment
    10|10000 characters needed characters exceeded

    • Plant is the delivering / supplying plant. The plant is ESSENTIAL as it helps in the determination of Shipping point. Shipping pt. is mandatory for the creation of a delivery.

      WH # is the warehouse from which goods have been picked.

      When you activate WM or Lean WM, then you see Plant and WH # in the delivery in Tab Picking.

      FYI - assignment of WH is done to Plant and storage loc. in LE