cancel
Showing results for 
Search instead for 
Did you mean: 

Plant change for partially delivered sales order

parmanandshinde
Explorer
0 Kudos

We have two manufacturing plants A & B customer placed order for 100 MT(metric tones). Once PO received from customer we create SO as per stock available in plant A or B. suppose we create SO for plant A -100 MT and delivered material 16 MT. Now suddenly plant is shut down due to some reasons and we want to delivered material from plant B. In that case currently we create order for 84 MT for Plant B & change qty in plant-A as 16. if possible to change plant in SO after partial delivery will be easy for us. Plant will be changed by warehouse staff.

Kindly advice

Thanks

Paramanand

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

For partial delivery made line item, you cannot change the plant in sale order. You have to foreclose that line item to the extent what has been delivered.

If you have delivered the appropriate quantity to that plant then close the Line item if still some stock is pending against that line Item and add a new line item with that Material & enter the new plant in Shipping Tab.

jpfriends079
Active Contributor
0 Kudos

Hello

Once you have subsequent doc (like delv doc) for the sales order.

You can't change that in Sales order.

If you want to reassign the plant for the remaining quantity, created a separate item line for that with desired Plant and reduce the same number of quantity from the previous line item.

Regards

JP