We use SRM5.0 and we want to implement SC, now we want to make it possible to change the delivery date in the shopping cart when we approve.

This is needed if we request today but the approver didn't approve same day, therefore the requested day has to move the same number of days, that the approver has spend. Or else the deliver date will not be correct.

Do any of you know how to do this??

Best regards

Jakob

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Sep 24, 2011 at 08:51 PM

    Hi Jakob,

    What scenario do you use? Classic, Extended Classic, Standalone?

    So depending on your scenario you can have differente types of follow-on documents (PR/PO only in ERP in case of Classic, or PO in SRMand ERP in case of Extended Classic).

    Do you use Sourcing Cockpit?

    I've tested this scenario in SRM 7.0 Standalone and if the follow-on document (in my case, a PO) is not "Ordered" yet then I can change the SC. But if it is already "Ordered", I can't change the SC. This is standard behavior.

    You could use Sourcing Cocking to solve this issue, in this you don't use it yet.

    Best regards,

    Christian Zeuch

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.