on 09-16-2011 10:43 AM
When changing requirements in MD04, the planning file entry for NETPL is only updated if the requirement is in the plant horizon, instead the horizon defined for the MRP group.
Then, when executing the MPS using the NETPL processing key, the system does not take into account materials with changes made in the MRP group planning horizon.
I have found a couple of SAP Notes describing similar problems, but any of them can not be applied to our version installed (ECC 6.0):
Note 680541 - MD62: Planning horizon not dragged from MRP group
Note 92026 - Incorrect indicator in planning file
Best regards,
Hi,
Please cross check the below settings.....MRP groups are defined with these specific control parameters and are assigned to the material in the material master record (MRP 1 screen).
For example, the following control parameters can be set for the total planning run:
the creation indicator for the plarequisitions, MRP lists, and so on)
the planning horizon
the consumption mode
The following is valid for total planning and single-item planning:
for all materials without an MRP group, the system uses the plant parameters, or the entries in the initial screen of the planning run
for all materials with an MRP group, the system uses the parameters recorded in the MRP groupnning run (creation of purchase
I hope this will help you.Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for the answer, but this is not the problem.
I have checked the parameters assigned to the material in the material master record (MRP 1 screen). The material is assigned to a concrete MRP Group, but the system is applying the plant planning horizon instead teh MRP Group planning horizon.
Thank you for the answer Kuber, but this is not the problem.
The material has MRP Group assigned in the material master record (MRP 1 screen), but the problem is that when changing requirements in MD04, the planning file entry for NETPL is only updated if the requirement is in the plant horizon, instead the horizon defined for this MRP group.
The problem is very similar than the described in the following SAP Notes, but I am using the ECC 6.0 version andI can not apply these SAP notes.
Note 680541 - MD62: Planning horizon not dragged from MRP group
Note 92026 - Incorrect indicator in planning file
Best regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.