Dear experts,
I am doing subcontracting POs por the vendor, I mean, I am doing a purchase orden with a line item of subcontracting with diferent components that I will send to the vendor.
After that I make the Outbound deliv. and good issue for the components.
the question is, who can I relate the Outbound deliv. with the purchase order? when i go to the purchase order I dont know if someone already sent the components to the vendor.
I would like othe way of doing this process, or any transacciones to relate the PO with de Outbound deliv.
Thank you very much for your help
Best regards,
Hi,
Purchase order history is not updated when you issue material to subcontractor.
Run report ME2O for details against subcon PO.
Thanks,
Anand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi........
before creating a new P.O please check in tcode mmbe stock at vendor
or check in mb51 material document if the document available with 541 mov means the stock given to vendor
then if not
create P.O with item cat "L"
then create outbound delv
issue the material mb1a with 541 movment
with reference with P.O no. then save
create subcontracting challan
then gr with referance with subcontracting challan
and then IR
Done
Neha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please note that in SAP standard, even though you issue the subcon components to the vendor using 541 mov.type with reference to the PO document in MB1B, the PO History wont be updated.
Hence as an alternative, you can check with user - exits to create a link between PO & the components issue.
Or you can use the standard SAP reports such as MBLB or ME2O where this information will be available.
You can also see reports such as MMBE or MB52 where the component stock will be displayed as stock with vendor (Special Stock - O) once component issue is completed.
Thanks & Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If they did transfer through MB1B without referencing the PO I don't think you can link it, if you have multiple POs lying around for a particular vendor which use similar components.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As you created subcontract purchase order for finished goods with different components and now you can send all different components to subcontracting vendor by two means
Option-1: issue components in t.code:ME2O directly
Option-2: issue components with t.code:MB1B with 541 Movement type
After sending you can check stock at vendor in MBLB t.code / can be used t.code: ME2O for subcontracting vendor stock monitoring
Finally you can do MIGO and then go for MIRO.
Regards,
Biju K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
But is there any way to link the document created in MB1B with the PO document number?
I mean, if I know de PO number, who can I know if the components has been sent? I have to go to other transaction and see for this vendor and this compnent if the material has been sent, but I dont see any trace from the PO to the issue document.
thanks
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.