on 09-15-2011 12:11 PM
Hi Everyone,
Does any one have idea about how to get cost in CN41N report? how to generate this report?
what is CJ40?
Thanks adv.
Hi,
Luckysoni,
1. CJ40 :- PS Tcode for Cost Planning of WBS elements .
2. CN41N :- PS Infosystem report, In IW32 -->Additional Tab -->If u have given any WBS elemnt , then Maintenance Order cost will reflect in this report under planned or commitment based on the settings in OPSV. You need give a PS Info profile ..
3. If u have settled MO Cost to WBS then i believe it would reflect as Actual Cost in CN41N under the WBS.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thnx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
CN41 / CN41N / CNS41 :- all of these are project structure overview report from SAP where in you can see the project in its structure (including all its assignmnets) format and also the cost / revenues asssociated with it.
If you have any maintenance order or a production order taht is assigned to WBS, then that also will show up in this report.
CJ40:- is for manual cost planning in WBS Elements. You can update plan cost of WBS Elements using this transaction. Please read more about this on SAP Help documnetation.
Regards
Sreekanth
Edited by: Sreekanth P S on Sep 15, 2011 9:00 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.