CN41N and CJ40

Former Member
0 Kudos

Hi Everyone,

Does any one have idea about how to get cost in CN41N report? how to generate this report?

what is CJ40?

Thanks adv.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Luckysoni,

1. CJ40 :- PS Tcode for Cost Planning of WBS elements .

2. CN41N :- PS Infosystem report, In IW32 -->Additional Tab -->If u have given any WBS elemnt , then Maintenance Order cost will reflect in this report under planned or commitment based on the settings in OPSV. You need give a PS Info profile ..

3. If u have settled MO Cost to WBS then i believe it would reflect as Actual Cost in CN41N under the WBS.

Answers (2)

Answers (2)

Former Member
0 Kudos

thnx

Former Member
0 Kudos

Hi,

CN41 / CN41N / CNS41 :- all of these are project structure overview report from SAP where in you can see the project in its structure (including all its assignmnets) format and also the cost / revenues asssociated with it.

If you have any maintenance order or a production order taht is assigned to WBS, then that also will show up in this report.

CJ40:- is for manual cost planning in WBS Elements. You can update plan cost of WBS Elements using this transaction. Please read more about this on SAP Help documnetation.

Regards

Sreekanth