Hi
Is it posible to do quota correction for number of employeees in one go. Unable to do from SE16.
Regards
RKGSAP
Hi,
If your using time evaluation and Quotas generating through time types/Round off number then you have to go IT2013/IT2012 through BDC or LSMW for first time upload of Quota/Quota correction.
If there is no time evalution you can upload IT2006 with BDC or LSMW.
Note: you should be consider if any latecoming deduction of Quota, accumulation of Quota, Quota transfer and Quota encashment is there Better go with time evaluation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Can you try to do that in PA70?
Regards;
Okan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
with my understanding on you question..!
you can try this through LSMW or BDC.
Thanks
Umakanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.