Hello,
I use IMCCP3 to copy cost planning to budget.
It works fine, except for closed WBS Elements.
In my selection screen, I can select a "Status Selection Profile".
I created such a status, that I called "Z00003", which select only REL and OPEN project.
It works fine in a report, as I can ask him to give me projects AND WBS elements with the Z00003 status selection profile.
But in IMCCP3, it doesn't work as I want. If there is a cost planning on a CLSD WBS, and the project is not closed, I have an error message.
Do you have any idea to help me telling the system not to take these CLSD WBS ?
Many thanks in advance,
Sandrine