on 09-15-2011 5:12 AM
Hello Folks,
I am using campaign optimization and after the campaign optimization is achieved by the optimizer the clean out order will be introduced. The clean out is overlapping with the actual operation on the resource.
The resources used are finite resources and alert is getting generated stating that the resource is overloaded.
The clean out order is expected to be sequenced correctly after the actual operation.
Kindly let me know if anybody has faced this issue and have a solution for it.
Let me know if you need any other details.
Best Regards.
Roopesh
Hello Folks,
This issue is solved.
Maintain the production time of the clean out order as the setup transition time among the same group in set up matrix, so basically after the number of charges defined in the campaign profile the optimizer will consider the time mentioned in the matrix and will create the space to fit the clean out order.
Regards,
Roopesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.