Error in scheduling agreement

Former Member
0 Kudos

Dear Experts,

We are facing error while doing GR for scheduling aggrement.

we have done the following steps.

1) Scheduling aggreement in ME31L

2) Released in ME35L

3) Mainatined Sch.Agmt Schdule in ME38 for todays and date 200 qty and other line is 800 qty.

When we are trying to do GR in MIGO system is giving the following message.

Document 5500000152 does not contain any selectable items

can I know what I have missed in the above steps.

Please guide me to resolve this.

Regards,

Prasad

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hey Prasad,

Since you are having 2 line items in your schedule line, at the time of MIGO when you give purchase order number there is one more textbox is there besides purchase order textbox...

for the first line item (i.e. for 200 qty ) give purchase order as : XXXXXXX 10

wenever you want to do GR for second line item (800qty) give purchase order as : XXXXXXX 20

I hope it works,

Regards,

Mehul

Former Member
0 Kudos

Hi Mehul,

Thank you for quick response.

I have tried that also. Still the error is coming.

Regards,

Prasad

Former Member
0 Kudos

Hey Prasad,

Plz check in the material master purchasing tab, JIT Schl. Indicator at the bottom.

If it is blank, give 1 i.e. Automatic.

it will create PO automatically, then you can try MIGO.

Regards,

Mehul

Former Member
0 Kudos

Hi,

please check below links...

Kuber

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

check the plant code in the MIGO .If plant code in PO is different from the MIGO will get this error.

Thanks.

Lakshmipathi
Active Contributor
0 Kudos

Moved from sales forum to MM forum

G. Lakshmipathi