Former Member
Sep 14, 2011 at 08:35 PM

How to assign a different factory calendar for cycle counting

293 Views

Hello - Is it possible to assign a different factory calendar for cycle counting than the factory calendar for the plant? To explain, we have assigned a 5 day work week calendar to our plant. This is because Purchasing and delivery dates operate on a 5-day work week. But cycle counting will occur 365 days a year and, therefore, requires the use of a factory calendar that operates on a 7-day work week.

For example, if I configure CC Indicator A to be counted once per year, using the 5-day work week factory calendar the interval between the last physical inventory and the due date of the next one is only 248 days. If I could use a 7-day factory calendar, the interval between the last physical inventory and the due date of the next one would be 365 days.

Anyone have any ideas on this?

Thanks