cancel
Showing results for 
Search instead for 
Did you mean: 

Planning time fence with Lot size MB

Former Member
0 Kudos

Hi Friends,

I am facing one issue as below,

I am using MRP type P3 , Planning time fence is 20 days , Lot size is MB (Monthly). I am not using MRP group.

Planning time fence should be calculated as Todays date+Planning time fence on MRP1 but if the calculated date with this formula is going in next month system takes first date of next following month as Planning time fence (effect of lot size MB).

WIth lot size EX , it works fine.

Can we avoid shifting of Planning time fence to first date of following month with lot size MB?

Thanks.

Sandeep

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

I got a workaround , I have used 2 lot sizing procedure in a sigle lot size. Daily lot size (for Short term) and Monthly lot size for Long term. For short term requirements are grouped for 28 days. Closing the thread. Thanks.

Former Member
0 Kudos

Check how the scheduling is set in lot size procedure. OMI4.

Former Member
0 Kudos

Using a planning calendar for the material can be a solution. You can define there which is the month start date for the orders.