Overall Network scheduling with out subnetworks

84 Views

Hi Guys ,

The issue is like this....

A project is structured with different Network headers and activities and possess relationships.

An activity from one network is linked to another activity of another network in the same project .

We are using forward scheduling functionality and also Network determines the project dates .

We would like to enter the start data at the first Network header only and system should generate the scheduled dates based on the relationships and durations to the other networks as well as activties also the start date of second network header is the finish date of first network header and this is how the flow is... .-In our case this is not happening and system is prompting to enter the dates at every network header level ... ...

Added to this....The entire scheduling be done using first the network header and system to schedule other networks and activities...

I have tried using CN24N , but getting an error message "No order corresponds to the selection criteria"

I have defined the leves for the order type in the spro and yet i am getting this message and could not schedule ...

Please suggest .....

Regards

Judy