I am getting error V1134 Account assignment cannot be carried out because of different origin no., when creating PO from PR. I have created sales order from quotation, and the SO generated automatically the PR in schedule lines. I am not getting the error when I start the process from SO, I am getting the error only when I start it with quotation (VA21).

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Please refer the below link

Hope it may help you.

Thanks.

Former Member
0 Kudos

Hi,

This would have caused because of program error...Pls apply the below note...but prequisite is Note 1234134 shd be already applied to your system...

NOTE : 1312488

I hope this will clear your issue .Thanking you

stevejohnson
Participant
0 Kudos

Unfortunately these notes are already implemented in the system, and I am still getting the error.

Could it be some problem with confoiguration? For example with the requirement class?

amitbakshi3
Active Participant
0 Kudos

Hi,

Please check the Document Type assignment of Quotation and Sales Order for the Process which is mapped and used in this process.

Best regards