on 09-12-2011 12:19 PM
I have created a DIP profile for resource related billing. The source is Actual Cost Line Items and I have maintained material determination for each relevant material and criteria with a cost element set and an activity type corresponding to the material in the material determination. I have two questions:
1. when I try to bill with this DIP profile in DP90, I get this message: 'There is more than one sales order or contract item for WBS element'. When I then restrict it to a single sales order item, it only pulls up the quantity i.e number of hours spent in the debit memo request with no costs attached. How can I get it to include costs? Also, I want to be able to bill several sales order items at the same time, how can I achieve this?
2. Time has been written to a WBS but in CATA, after approving the time written to the WBS, I get the message 'no records for transfer to PS'. Is this why the cost is not being billed? How do I correct this?
Hi,
Have you released the time entries and approved it before doing CATA?
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Fine. What are the settings that you have maintained in your DIP profile? Are you able to see the recorded times in any of the timesheet reports. Also check report CJI3 to check if you can see the actual costs for these recorded times. I am aware that CATA is not done. Just check in case it was executed before.
Settings for DIP Profile:
Usage - Billing and Result Analysis
Material Determination is a list of my service materials for which T&M is relevant
Criteria: Set for Cost Element, and a single activity type
Also cannot time write to the sales order assigned to the WBS. I get the error message "Account 943110 requires an assignment to a CO object"
Hi,
I understand from all the post that, you are using CATS for time entry.
If the receiver cost object is WBS element, transfer to PS will not happen. Only CO will happen when you are trying CATA.
Hope you are using activity type and cost center combination which is having the cost when you are entering CAT2.
If you are using network as a cost object with activity, PS transfer will happen for sure when trying CATA.
Check the report CJI3, Cost element line item report that, hours and cost is getting updated or no giving the WBS Element and posting date as a input.
In ODP1, hope you have mainatined activity type sets and also test with actual cost -line items and also total records.
If you are using the same WBS Element for multiple sales line items, you need to maintain line items using DP91 transaction.
Iam sure it should work.
Regards
N.Raju
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.