Skip to Content
0
Former Member
Sep 12, 2011 at 07:28 AM

Cost component split transfer for Profit center valuation in ke27

164 Views

Dear All,

We have activated multiple valuation/transfer prices. Material ledger is also activated.

We want to transfer cost component split to CO-PA by ke27.

We have defined separate costing keys for access to actual cost estimate for legal and profit center valuations.

But cost component split transfer to COPA works only for legal valution. Even we have defined type of valution for profit center costing key -transfer cost component split and total costs.

What should be else customized to transfer cost components splitting in profit center valuation to CO-PA from actual cost estimates?

With best regards,

Kamila.