Hello Expert,
We are getting the message "Data partly after horizon 01.09.2016 to 01.12.2017" while we load a material in planning book and run the heuristic below popup is appearing:
2- We have one Planned Order (fixed) for material XYZ01234 in plant S124 that is display in Planning Book in the line Production Planned instead of Production Confirmed :
We have run all the consitency check and STB and TBP are also fine.
please advise on the same.
Thanks,
Hi Jeet,
This can happen if the heuristic has created a receipt outside the horizon / date range which the Planning Area has been initialized with. In this case, the element created after the horizon will not be saved. If necessary, the Planning Area can be reinitialized with extended horizon.
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jeet,
As Tiago mentioned do check the planning area initialisation horizon as well as storage bucket horizon for the concerned planning area via /SAPAPO/TR32.
Thanks & Regards,
Sonali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.