Hello,

I need help about PP-CO integration.

I have a component which already has two production version, but I want to create a new production version in the middle of the month and I will start to use the new version. Is it problem for CO?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

4 Answers

Solomon Macwan Jan 19, 2017 at 06:40 AM
0

Hi Sevim,

I believe that you are using price control as S.

If you change a BOM, whatever price difference will come, it will show as a variance in costing. only if the price difference is too high than it will show in varince report.

Regards,

Solomon

Share
10 |10000 characters needed characters left characters exceeded
Shoyeb Ahamad Dec 19, 2016 at 02:04 PM
0

Hi Sevim,

Which scenario are you using there? Is it Discrete, Repetitive or Process industry?

As far as I know, there is no impact of having multiple PVs for one material because in CO you generally do your Standard cost estimate taking one PV into consideration.

Regards,

Shoyeb

Share
10 |10000 characters needed characters left characters exceeded
SEVIM ERDOGAN Dec 20, 2016 at 08:42 AM
0

Thank you Shoyeb,

I use disctrete industry. My problem is, I will create a new PV and start to use the new version in the middle of the month. As far as I know CO do the standart cost estimate before using the material and begining of the month.

I hope I could explain myself clearly.


screenshot-2.png (2.6 kB)
Share
10 |10000 characters needed characters left characters exceeded
Anupam Sharma Jan 19, 2017 at 06:07 AM
0

Hi Sevim,

Since you cannot have another cost estimate for the same material for the same period, also it depends your co configuration whether you are working with Mixed costing or not?

Regards,

Anupam Sharma

Share