on 09-09-2011 8:07 PM
Hi all, we're triyng to update field plant for RFQ (Request For Quotation) that was created with reference to a RFP.
We tryed updating T162 via SPRO to allow this, but was unsuccessfull.
Does anybody know how to do this without an ABAPER?. Were running ECC 6.0
THANKS IN ADVANCE.
.....................................
Edited by: Juan Manuel Caballero on Sep 9, 2011 9:11 PM
Hi Juan,
I don't think this is possible. You see, only the "new design" transactions (ending with xxxxN) allow changing of plant. The old transactions simply don't have provision for this, since such change requires very sophisticated checks and follow-on updates.
Unfortunately there's no "new design" transaction for RFQ's as yet. You will have to create a new RFQ.
BR
Raf
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.