on 09-09-2011 7:32 AM
Hi Experts,
My client wants changes the current Internal Order BUget checking. Currently Budget checking happens with availability control ie. 105% Suppose current budget is 8000. It will add 5% and Purchase reqn checks the fund available with 8400 less budget utlised, but client wants 8000 less budget utilised as they want to keep 5% aside for the unforseen cases.
Cilent does not want to change the current availability setting i.e 105%, retaining that availability check, client wants to check the availability excluding tolerance. What is the solution for this.
Appriciate your immediate response.
Thanks & regards
Veda Pandit
Hi,
I think you shall set 100 % limit for purchase order and purchase requisition and 105% for good receipt.
You can do so in customizing "Define Tolerance Limits for Availability Control" , using the activity group.
Paolo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.