Changes in Budget checking during creation of purchase requisition

Former Member
0 Kudos

Hi Experts,

My client wants changes the current Internal Order BUget checking. Currently Budget checking happens with availability control ie. 105% Suppose current budget is 8000. It will add 5% and Purchase reqn checks the fund available with 8400 less budget utlised, but client wants 8000 less budget utilised as they want to keep 5% aside for the unforseen cases.

Cilent does not want to change the current availability setting i.e 105%, retaining that availability check, client wants to check the availability excluding tolerance. What is the solution for this.

Appriciate your immediate response.

Thanks & regards

Veda Pandit

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I think you shall set 100 % limit for purchase order and purchase requisition and 105% for good receipt.

You can do so in customizing "Define Tolerance Limits for Availability Control" , using the activity group.

Paolo