Please suggest what is the differance between CA60 and CA61 transaction? When it is advisable to use CA60 and when CA61?
rEGARDS,
Hi Abhay,
CA60 (Report RMPLAN00)- Changes in Routings/Ref. Op. Sets-> Gives all the Task list changes occurred at object level (detailed change documentation) say change in operation, component, PI characteristics etc. with whole description like changed dates, user name, change no etc.
CA61 (Report RCPCD002)- Change Documents for Routing
Change Doc View->Gives overview of change documents, i.e, changed dates,user and what Tcode made changes
Object View for routings->Gives overview of the changed objects with old and new values
In both the cases the selection objects are almost same except CA60 gives detailed changes like operation relationship also.
Thanks
Sree...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.