Skip to Content
author's profile photo Former Member
Former Member

J1iin !

CIN Experts Help Needed

My Requirement

1. Pricing to be modified at the time of J1iin

2. So that i get the accting entry

Inventory Dr 100 [ for the receiving unit with Material cost + Excise cost))

Cenvat Clear

Inventory Cr. 90 { for the despatch unit with the Material cost)

Cenvat Clearing 10 ( For the receing unit with the ED payment amount)

This is done to map the below mentioned senario

1. STO between plant ( one would be excisable and the other would be non-excisable )

2. Price is MAP- ( Add the centvat to the cost of material )

How to go about this !

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Sep 08, 2011 at 09:52 AM

    At the time of Outward STO, inventory accounts do not get hit. The Inventory related adjustments happen at PGI for both Receiving and supplying plants.

    This is not possible through Standard J1iin.

    Dany

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.