Former Member
Sep 08, 2011 at 07:42 AM

Shift Factor for late completion

480 Views

Dear all,

Here i have a requirement

i have created a maintenance plan with cycle -10 days

Shift factor 80%

Tolerance 20%

Cycle start:22.08.2011

Scheduling period:30 days

Schedule calls were

Plan dates:

01.08.2011

11.08.2011

21.08.2011

But first completed on 04.09.2011 delayed by 3 days,

Plan date Completed date Act variance

01.08.2011 04.08.2011 3 Days

According to shift factor (80%) my next call will be 80 % of 10 days Ie) 8 days from completion date (04.08.2011) will be on 12.09.2011.

But i got next calls on 13.09.2011,23.09.2011

How system is calculating second plan date?

Somebody pls analyse it

Thanks in advance