Dear all,
Here i have a requirement
i have created a maintenance plan with cycle -10 days
Shift factor 80%
Tolerance 20%
Cycle start:22.08.2011
Scheduling period:30 days
Schedule calls were
Plan dates:
01.08.2011
11.08.2011
21.08.2011
But first completed on 04.09.2011 delayed by 3 days,
Plan date Completed date Act variance
01.08.2011 04.08.2011 3 Days
According to shift factor (80%) my next call will be 80 % of 10 days Ie) 8 days from completion date (04.08.2011) will be on 12.09.2011.
But i got next calls on 13.09.2011,23.09.2011
How system is calculating second plan date?
Somebody pls analyse it
Thanks in advance
R.A.Kiran