on 09-06-2011 1:51 PM
I am getting an error "Purchasing document has release indicator R (changes not possible)" while updating delivery complete indicator in Purchase order using MASS change transaction. I have set changeability of Purchasing Document for release indicator as 1 in release strategy due to which it is not allowing to change the PO. So please suggest solution to bypass this error while updating the delivery complete indicator.
Hi,
You could try will indicators 4 and 6
Regards
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
With release indicator as "1", you would not be able to change the Purchasing documents for which the release strategy has been triggered. Change the Changeablity indicator in the Release indictor to 2/3/4 and then proceed with Msas change. Later you can reset the value to 1.
Hope this helps.
Thanks and regards
Hemanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Aruna,
You cannot Bypass this. You can solve this in 2 ways.
1. Temporarily change it to 2
2. Do the changes (setting del compl indicator) before release.
Suraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.