Dears

In my quality department we have 5 person

3 persone is working on inspection ..so their cost is capturing while recording the result

but other 2 person working general prevention activty..so i can not cach any cost as they are not part of Inspection

So there is any possibilty is there to capture their cost to any QM order

Faisal

Accepted Solutions (1)

Accepted Solutions (1)

anand_rao3
Active Contributor
0 Kudos

Dear Faisal,

I beg your pardon, but I am not so sure what exact cost you want to capture? Whether the salaries of the personnel working with inspection department or you have some activity whose rates per hour or minute are known to you. If you could please explain the exact role of these personnel and logic of capturing cost.

1. Conceivably QM order may not address this issue.

2. You may think of using service purchase order in case of contracted hires. Settle their payments against service PO on QUALITY cost center.

3. You may create these employees as vendor codes and can pass direct entry of the cost against QUALITY cost center.

4. Have few words with your cost accountant in order to finalize where the exact effect should to reflect.

Regards,

Anand

muhamed_faisal
Active Participant
0 Kudos

Dear Anand

I am try to capture the cost of Quality department person other than who involve in inspection activity

those who involve in inspection activity their cost is capture against QM order

But those who dint involve in inspection activity their cost also need to capture that is what i try to achive

Faisal

anand_rao3
Active Contributor
0 Kudos

Then its nothing but the salary or payment that these persons receive. As per my understanding there are 2 ways to do this. Settle payment against service PO or settle it against creating vendor code. CO consultant can give you more insights about this.

Regards,

Anand

Answers (2)

Answers (2)

former_member207800
Active Contributor
0 Kudos

You can refer the concept of activity-based costing of controlling module.

In my experience some company implemented those function for analysis of total quality cost.

Regards

Luke

Former Member
0 Kudos

In KB21/KB21n you can do the same.

You have to create activity type.Then there is one sending cost center & one receiving (in this case its Quality cost center)

muhamed_faisal
Active Participant
0 Kudos

hi

here what is the sending cost center

Any need of QM order here

Pls explain

Faisal

Former Member
0 Kudos

Generally Quality assurence & Quality control have different cost centers.

So you can check relevant cost center or cost center for which peolpe are working.

I am not sure about the QM order here as its not department specific.

muhamed_faisal
Active Participant
0 Kudos

Dears sujit

in this case sender cost center is Inspection cost center

and receiving cost center is Quality cost center

Pls verify above methode is correct or not

Normaly KB21N we are using for Non confirmance cost recording/Failure cost

Same methode can be used here also?..Pls verify