Skip to Content
0
Former Member
Sep 03, 2011 at 06:33 AM

S_ALR_87013532 report -plan cost not rolling upto the WBS/Project level

202 Views

Dear All,

Plan cost from production orders is not rolling up to the WBS/Project level in S_ALR_87013532 ( Plan/Actual Variance report).

Where as plan cost from network is properly rolling up to the WBS/Project level in the above report.

Please suggest what could be the reason for this issue. Is any configuration needs to be done for this.

Thanks & Regards,

Vishal