Hello,

We need to prevent confirmation of a maintenance order toa particular WBS element. We have updated the status profile on the WBS elements to prevent any postings or assignments or confirmations to it.

But there is something we need to do from Plant maintenance side on the PM order to prevent the confirmation to that WBS. Please provide your valuable inputs on how to do this.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 01, 2011 at 03:40 PM

    Please include the following objects in your WBS User status based on your requirement

    Maintenance order

    PP/PM: operation

    PP/PM: order header

    Please try and let me know