Skip to Content
0
Former Member
Aug 30, 2011 at 06:10 AM

Incorrect Plan values on S_ALR_87013533

244 Views

Hi experts,

We are planning projects via material components to network activities.

Issue over here is initially few materials were having MAP value as

zero & those materials have been used for project planning.

So plan values were based on those zero values & plan value was not

100% correct.

Now we have updated material master with correct MAP value, but still

on S_ALR_87013533 report shows incorrect plan values for said project.

Is there way to update those projects with correct plan values without

reassigning materials to projects in order to reflect correct plan

values on S_ALR_87013533 report?

Beat regards,

SL