on 08-29-2011 7:55 PM
Hi
I have one issue in commitment
When I am creating service Purchase order the value of PO i can see in report "s_alr_87013558" as commitment cost
but
when I create Standard Purchase order that time value of PO not showing in same report.
I am new in PS please help me.
thank you.
Hi sudhir_sap_sd ,
As my colleague has suggested note 152571 should help to solve your issue. I have outlined the following steps which I feel should fix the inconsistencies you are currently experiencing.
1) Please run report RKANBU01 for the incorrect projects in question. This will update any incorrect commitments. Further details can be found in the note above.
2) After running the reports above, please run report RKACOR04 as this will correct any problems between the line item tables
and the total record tables.
3) After running the above reports, please run transaction CJEN for all the projects as this is very important so that the database gets updated.
4) Finally run report CJBN which rebuilds the availability control for each project.
Many thanks and kind regards,
Enrique
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Similar question is already posted in the forum. So please do search the forum and see if you can find the answers for your question. Also please check the note 152571.
Regards
Sreekanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.