Hi Experts,
Issue: Activity price in CK11N showing a different cost than expected.
We have set 'plan price for the period' in valuation variant.
Plan price indicator in activity type = 1 (plan price automatically based on activity)
KP26 : Same price for all periods ( So I assume distribution key wil not affect the calculation Anyhow we have given 0 (manual distribution))
In CK11N output, Activity quantity/unit (machine hours) is picked correctly (eg: 1 hr)
In CK11N output, Activity price /unit (Amount) is picked correctly (eg: Rs.10 per hour )
But the value of activity is showing a different quantity (eg: Rs 8.5 which is not equal to 10x1)
Work center capacity utilization is 100%
More importantly in the production order when actual confirmation happens, the activity value is coming correctly! (Rs.10)
Valuation variant of the actual values in production order is also 'Plan price for the period'.
Is there any other factor/setting that affects activity price calculation?
Does disribution key affects activity price calculation even if the values for all the periods are same?
I'm doing the CK11n on 28th (today) does that affect the calculation by any chance?
Quick reply is appreciated.
Best Regards
Vimal