Hi All,
While creating rework PO, i get the following error.
" Ship. condition loading grp 0001 plant Stloc not defined"
Message no. V1358
What should i maintain to overcome this error.
Please advice.
Regards
Hi
I guess the problem lies in Shipping point determination
check the entry make sure the below combination
shipping piontloading groupplantprefered shipping pointmanual shipping point
Path: IMG-logistic execution-shipping-basic shipping functions-shipping point and goods receiving point determination --> assign shipping points.
(if you have already created the delivery make sure the shipping ponit is same in order and delivery (make sure no one has changed in sales order -- i have seen this error before)
Kindly check the below
1. T code OVL2 and OVL3
2. shiping conditions maintained in the customer master
3.Assignment of shipping point to Plant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You will have to maintain the Loading group in Material master "Sales General Plant data". Shipping condition is maintained either in Customer or Vendor master.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Pl. check the shippoing point determination in customizing
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.