Hi Guru,

Is there any possibility in standard SAP to calculate Running Hour based MTBR.

The situation is my client operate equipment only 8 hour/per day where as SAP assumes equipment running 24 hrs/per day in MCJB (for numerator in MTBR , denominator is fine)

Thanks for help

Ashok M

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Dec 19, 2016 at 02:08 AM
    • So far there are no solutions available known to me for such requirements in standard.
    • But I believe a solution can easily be reachable through an ABAP program, logic for with is not very difficult.
    Add comment
    10|10000 characters needed characters exceeded

  • Dec 21, 2016 at 08:06 AM

    Thank you Jogeswara.

    is there ant FM should I use in this custom report rather than reading SAP PM table?

    Thanks

    Ashok