Hi Guru,

Is there any possibility in standard SAP to calculate Running Hour based MTBR.

The situation is my client operate equipment only 8 hour/per day where as SAP assumes equipment running 24 hrs/per day in MCJB (for numerator in MTBR , denominator is fine)

Thanks for help

Ashok M

Accepted Solutions (1)

Accepted Solutions (1)

jogeswararao_kavala
Active Contributor
0 Kudos
  • So far there are no solutions available known to me for such requirements in standard.
  • But I believe a solution can easily be reachable through an ABAP program, logic for with is not very difficult.

Answers (1)

Answers (1)

former_member245085
Participant
0 Kudos

Thank you Jogeswara.

is there ant FM should I use in this custom report rather than reading SAP PM table?

Thanks

Ashok