Cost element is POC relevant

Former Member
0 Kudos

Hi experts,

How can i identify whether a cost element is POC relevant or not? Please advise.

Regards,

Udaynath.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

One way is to check wheter this cost elemenst is used RA configuration for assignments and updatewith appropriate line id combination. If yes, then the cost incurred in this cost elemnet will be considered for PoC caluclaion during RA.

Regards

Sreekanth

Former Member
0 Kudos

Thanks Sreekant for the reply. But is there any configuration settilng by which i can check the cost elements is POC relevant.

Regards,

Udaynath.

Former Member
0 Kudos

Hi,

Yes, check the RA configurations like OKG4, OKG5.

Regards

Sreekanth

Answers (1)

Answers (1)

former_member230675
Active Contributor
0 Kudos

> How can i identify whether a cost element is POC relevant or not? Please advise.

Display the cost element in KA03 and check the CElem category under Basic Data. Click that field and get F1 Help to know more about the Cost Element Category for Primary Cost Element Categories and Secondary Cost Element Categories.