Hi PM Gurus,

When we create a maintenance order, for the component the Reservation is created. The components is externally procured with the some planned delivery dates. but during the MRP run these Planned Orders are not converted to PReqs automatically. checking the planning file entry there in no planning file entry created therefore MRP has not considered it.

Now we are using MD15 to collectively convert the Planned Orders to PReqs.

The Item category of these spare parts are "L". Please suggest if what configurations are to be checked, maintained in order for MRP generate the PReqs from the Planned Orders.

Thanks,

Nag