on 08-24-2011 7:42 AM
Hello,
I already activated "time-dependent conditions" in IMG for Schedule Agreement
and I have maintained the following info record,
2011.08.15 2011.08.24 1.00 HKD 1 PC
2011.08.25 2011.09.23 2.00 HKD 1 PC
2011.09.24 9999.12.31 3.00 HKD 1 PC
when i create a Schedule Agreement, i input "Validity Start" 2011.08.23, "Validity End" 2012.08.24. the Agreement Date is 2011.08.24. when i go to "item conditions", here only display a info record i.e current info record 1.00 HKD per 1 PC, and the Valid From 2011.08.24 Valid to 9999.12.31
however the effective period of the schedule agreement go through all info record, WHY the conditions in future periods are missing in the schedule agreement?
Hi
If you have maintain the conditions in the info record then it will automatically copy to the scheduling agreemnt.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Check the condition record in MEK3 for the key combination "Material Info Record" , whether any record exists on the Valid on date as required by you.If not you will have to maintain the same.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.