Former Member
Aug 24, 2011 at 06:01 AM

Planned date problem after MRP Run

180 Views

Hi Experts,

I have Finished Product FG01 in which 2 levels of BOm is there ie SF01 & Sf01 & all Raw materials.

Planning strategy for FG is 40 (Planning with Final assembly).

I have generated PIR in Md61 for FG for date 25.08.2011. For RM I have maintained Planned delivery time 5 days & GR processing tome 1 day.

While running Mrp in MD02 I have selected Lead time for Scheduling ie it will calculate lead time from routing data.

After running MRP I found that my RM planning is done accurately ie proper 6 days have been taken by the system to bring RM in stock.

But the problem is for FG & SFG planned order start date is 25.08.2011 which is wrong & it should show the date after RM comes in Stock.

So Experts I want ur help as its very urgent & demanding for my client.

Please reply fast.