error material not maintained by purchasing when creating info record

Hi Expert,

I have an issue when creating info record, error says "Material ******* not maintained by purchasing". I've checked in MM03 purchasing view, all has been maintained and at the bottom there is message says "No plant-specific data exist". Accounting view also maintained. I've also checked in MARC table for this material and plant. It existed. I cannot see anything wrong on the material master setup but not sure why am i having this error...

Please help.

Thanks,

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Aug 24, 2011 at 02:19 AM

    Check MARA-PSTAT for Maintenence status whether you have the below indicators for the relevant views.

    A Work scheduling

    B Accounting

    C Classification

    D MRP

    E Purchasing

    F Production resources/tools

    G Costing

    K Basic data

    L Storage

    P Forecasting

    Q Quality management

    S Warehouse management

    V Sales

    X Plant stocks

    Z Storage location stocks

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 24, 2011 at 02:41 AM

    Hi,

    Error says "Material ******* not maintained by purchasing" & you checked purchasing view has been maintained.

    OK. Just cross check following optionS

    Option-1: You creating info- record for material with combination of plant & vendor....check did the material have purchasing view for same plant-the info-record you are creating!

    Option-2: If no purchasing view for material with same plant , just extend in t.code MM50 for E Purchasing

    Option-3: Check the material for same plant, did Procurement type F (External procurement) is there

    Option-4: Check Profit Center in Plantdata/ sto-2 view of material.

    Regards,

    Biju K

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 24, 2011 at 02:45 AM

    Sorry Vijay, i don't understand on the 1st option. What do u mean by

    "check did the material have purchasing view for same plant-the info-record you are creating!"

    I'm talking about the same material same plant.and the purchasing view maintained in material master.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi

      There are two reason for this error

      1.Either your material is not maintained in purchasing veiw ( goto MM01 and extend the material for purchasing view)

      2.The maintanance status for the material (E-purchasing )is not maintained) check the X plant material status in BASIC DATA 1 view and plant specific material status in MRP 2 VIEW.( Goto MM50 extend the material staus fior E- purchasing for the material)

  • avatar image
    Former Member
    Aug 24, 2011 at 06:01 AM

    I've check PSTAT in MARC table for this material and plant. There's no E but VDLBG. What does it means??