on 08-23-2011 8:12 AM
Dear All,
We are Using Discrete Manufacturing Scenario, In That Scenario Routing Contains Six Operation and One or Two Operations having alternative Sequence , My client required during production Order Creation , If Operation quantity is more than 250
system should select std sequence else system should select alternative sequence, But i am not getting to mantain lot size for std sequence for operation even I maintaining lot size for alternative sequence , system should not considering alternative sequence. Pls Suggest me how to Resolve Issue
Thanks
Maintain Alternative sequence stating branch and return operation.Also maintain lot size for alternate sequence in your routing.
In customization of Order Type Dependent Parameter make the below settings
In Planning Tab, select
Selection ID : 01
Routing Selection: 3
Sequene exchange :1
Alternative Sequence: tick
Task List Type :N
Please check and revert
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Maintain Alternative sequence stating branch and return operation.Also maintain lot size for alternate sequence in your routing.
In customization of Order Type Dependent Parameter make the below settings
In Planning Tab, select
Selection ID : 01
Routing Selection: 3
Sequene exchange :1
Alternative Sequence: tick
Task List Type :N
Please check and revert
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Vipin,
It is not possible to control the routing sequence selection based on lot size.
As suggested by forum experts, create mulitple group counters for the same material routing group and you can use them based on lot size.
You can also create production versions for different lot sizes.
Check and revert,
Santosh Sarda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I suggest that instead of alternative sequences you use alternative routings. It is basically similar, but in this way you can have an automatic determination based on quantity!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.