Former Member
Aug 23, 2011 at 07:04 AM

Difference in delivery date between SC and PO

57 Views

Hi!

We are in SRM 4.0 ECS SP 12.

When creating SC with catalog items, delivery date at item level is getting updated based on the leadtime comming from catalog OCI. When user change that in SC to a new delivery date, the follow-on PO is not updating with the changed date. Instead it is

calculating the delivery date based on the leadtime passed from catalog.

Is this a standard functionality? We want to have the delivey date in PO item same as that of SC item. How to accomplish that? Is there SAP Note available for this?

Br, Prasad