on 08-22-2011 9:20 AM
Hi,
During external services(control key PM03), system picks up default cost element in maintenance order. Irony is that I have set no default cost element in "External procurement service in Config". I have also checked there is no default user data, despite this default cost element system picks up.
Please suggest me what to do.
Thanks & Regards
D.Singh
Once you enter the control key PM03, you will get pop up for maintaining material group. If you have defined the material group in config, cost element will be picked up from that.
Cost element will be picked up from the Material group which you mentioned in Order or in config.