Prod Order Type Automatic selection

Dear Sir,

In MTO, after MRP run, during the conversion of planned order to production order, how system detect the production order type automatically if I have more that one production order type.

Thanks and Regards,

Chetan

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Aug 22, 2011 at 06:37 AM

    Hi,

    In customization for MRP, you define per plant the default order type for conversion of planned orders.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 22, 2011 at 06:45 AM

    Dear,

    While converting planned order into production order system fetch order type from production scheduling profile maintained in material master. kindly check production scheduling profile in OPKP.

    Thanks

    Muhammad Ashfaq

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 22, 2011 at 07:12 AM

    Dear ,

    Please check OVZG setting for requirement class ( check based on your stratergy) , check whether any order type is maintained or not?

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.