on 08-22-2011 7:32 AM
Dear Sir,
In MTO, after MRP run, during the conversion of planned order to production order, how system detect the production order type automatically if I have more that one production order type.
Thanks and Regards,
Chetan
Hi,
In customization for MRP, you define per plant the default order type for conversion of planned orders.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Chetan,
1.Check if the production scheduling profile/production scheduler has been assigned in the material master.
2.If only production scheduler has been maintained means,then in OPJ9,check whether this prod.scheduler has been linked to
prod scheduling profile(through which the default order type can be set),if only prod scheduling profile means then directly check
in OPKP for this profile what is the order type.
3.IF no prod.scheduler/prod scheduling profile has been maintained means check whether any MRP group has been assigned in
MRP1 view which has the default production order type settings in OPPR.
Check and revert back
Regards
Mangalraj.S
Edited by: Mangalraj.S on Aug 22, 2011 12:37 PM
Dear ,
Please check OVZG setting for requirement class ( check based on your stratergy) , check whether any order type is maintained or not?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
While converting planned order into production order system fetch order type from production scheduling profile maintained in material master. kindly check production scheduling profile in OPKP.
Thanks
Muhammad Ashfaq
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.