Procurement at the beginging of the period

Hello,

Demand is maintained in the system in month format, which the system splits into weekly buckets and procurement proposal is generated accordingly (based on weekly production plan). We would like to procure certain parts at the begining of the period and would like the system to generate planned orders for the begining of the period instead of dividing it over the weeks.

What parameters can be used in MRP to make this happen.

Thanks

Mira

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Aug 22, 2011 at 06:32 AM

    Hi,

    A simple method may be using a monthly lot sizing procedure for the material. This way requirements for a month will be grouped into one proposal at the beginning of the period.

    Regards.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.