cancel
Showing results for 
Search instead for 
Did you mean: 

Procurement at the beginging of the period

Former Member
0 Kudos

Hello,

Demand is maintained in the system in month format, which the system splits into weekly buckets and procurement proposal is generated accordingly (based on weekly production plan). We would like to procure certain parts at the begining of the period and would like the system to generate planned orders for the begining of the period instead of dividing it over the weeks.

What parameters can be used in MRP to make this happen.

Thanks

Mira

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

A simple method may be using a monthly lot sizing procedure for the material. This way requirements for a month will be grouped into one proposal at the beginning of the period.

Regards.

Former Member
0 Kudos

Thanks Ozgen.

I tried it and it is helpful, is there any other way ?