on 08-19-2011 10:32 AM
Dear All,
I am trying to transfer PDS to APO system using CFM1 and CFM2.
out of the 473 PDS, only 30 odd got transferred to APO. The remaining are not transferred and system is not giving any error message also.
The components of the BOM is not in APO, since they are not APO planned. Only the PDS, i.e the Routing have to be transferred.
All the Materials and Resources are already in APO.
The capacity and scheduling details are available in the work center.
The Routing and the BOM is valid. the material is also Valid.
The capacity planner group in ECC is also there in APO.
I am not able to find the error. Am i missing something with regards to the master data??
need your comments and suggestions in solving this issue.
Thanks
Nagendra Kumar
Hello All,
the problem got solved.
i think the error was with the inconsistencies in livecache..
i ran the report /sapapo/om17...
then transferred the pds again using cfm2 and all the materials got transferred.
regards
Nagendra Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.