PR through MRP..

Hi Expert ,

What all the configuration required to Generate PR through MRP..

Thanks in advance.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    Posted on Aug 18, 2011 at 12:42 PM

    you have to have a MRP type relavent to material planning , lot size, procurement type, strategy group for the independent material,

    checin, checking group for availability check ( in sales and operation planning of spro) which is to be entered in material master and checking rule and determine availablitity check in MRP >> planned orders

    in short you have to maintian the configuration in material requirement planning and enter sutitable values in MRP1 to 4 views of material master

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 18, 2011 at 03:10 PM

    HI

    Maintain the configration setting for consumption based planning .

    In material master maintain MRP VEIW 1 AND 2

    In MRP 1 you enter the MRP type and reorder point and lot sixe

    In MRP2 enter the procurement type and gr processing time and planned delivery time and also safety stock,

    Maintain a valid source in the source list in that select MRP indicator 1 ans save.

    Goto MD03 enter the materil plant and enter warning message will come enter one more time

    Systema will create a p.req quantity based on the reorderpoint enter in the material master.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 18, 2011 at 12:33 PM

    Hi,

    Please maintain the below settings for generating PR through MRP.

    1. Maintain setting in Consumption based planning in MM

    2.Use special procurement key

    3.Assign the same in MRP 2 view of MM

    4.Maintain a soursce list if req.

    5.Run MD03 and create PR

    6.Use ME57 or ME58

    You can also schedule a job for the same. This will automatically take care of converting PR to PO. To automate the process of PO creation..then do all above basic settings along with the following settings:

    1. Auto PO indicator in VMR and MMR

    2. Maintain the sourcelist with relevent source and can also make it fix with the FIX indicator...

    If you wanna make the schedule lines then need to use the MRP indicator as 2 in the source list..you can't get PO as the result of MRP run in standard system - you get only PR & you have to convert the PR to PO .

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.