Planed order splitting & sequential scheduling according to max lot size

357 Views

Hi,

The scenario is MTO, requirement is if sales order with big lot is inputted, then after MRP run instead of single planned order - number of planned orders to be created with sequential scheduling according to max lot size entered in material master.

I tried to select "lot size with rounding" under MTO lot in EX lot size procedure configuration, now planned order is splitting and all start date is same but I want to have scheduling sequentially like for 20th 1 planned order, 22nd 1 planned order, 24th 1 planned order....... according to max lot size till the Big lot is planned. Require in backward scheduling.

Thanks